Krishna Drinking Water Supply Project
Background:
- Krishna Drinking Water Supply Project envisages for tapping 16.5 TMC of raw water from river Krishna i.e. 270 Mgd, in three phases each phase of 5.5 TMC raw water tapping for adding 90Mgd of treated water to the water supply system of Hyderabad Metropolitan area in each phase.
- Programme of Implementation of Krishna Water Supply Project:
Sl. No. |
Phase & Stage / Year |
Raw Water Tapping per Annum |
Quantity of additional treated water to be added (in Mgd) per day |
1. |
Phase-I |
- |
- |
- |
- |
a) Stage-1 (2002-2004) |
2.75 TMC |
45 Mgd |
90 Mgd |
|
b) Stage-2 (2004-2006) |
2.75 TMC |
45 Mgd |
2. |
Phase-II (2006-2011) |
5.5 TMC |
90 Mgd |
90 Mgd |
3. |
Phase-III |
- |
- |
- |
- |
a) Stage-1 (2011-2016) |
2.75 TMC |
45 Mgd |
90 Mgd |
- |
b) Stage-2 (2016-2021) |
2.75 TMC |
45Mgd |
- |
Total: |
16.50 TMC |
- |
270 Mgd |
2.1 The Stage-1, Phase-I of the Krishna Drinking Water Supply Project to transmit 45 Mgd of treated water estimated to cost Rs.875 Crores (Rs.1000 Crores including interest during construction) has been taken up and about 60% of the Project is completed and it is programmed to complete the Project by 31st Mar'2004. The raw water required for the Stage-1 of the Phase-I Project is proposed to be tapped from the AMRP Main Canal at Km 26.328 as a time being arrangement.
2.2 The Stage-2 of Phase-I Project is to add another 45Mgd of treated water and is programmed to be taken up and completed by end of year 2005. In Stage-2, an independent intake tower would be constructed in the foreshore of Nagarjuansagar at Shunkishala and raw water would be pumped to the WTP at Kodandapur. This would be a permanent arrangement for drawing required raw water of 5.5 TMC from Nagarjunasagar, River Krishna, to the Krishna Drinking Water Supply Project.
HYDERABAD METROPOLITAN WATER SUPPLY AND SEWERAGE BOARD
Krishna Drinking Water Supply Project
Water Allocations:
- The Government vide G.O.Ms.No.264, dated: 29-12-1997, I&CAD Department (PW-NSP) has ordered providing 8.25 TMC of water for drinking purposes to the twin cities of Hyderabad & Secunderabad, from Nagarjunasagar Reservoir.
- The Government vide G.O.Ms.No.70, dated: 4-5-2002 of I&CAD Department (Project Wing - SLM), Government agreed and issued orders to supply raw water from Akkampally Balancing Reservoir of AMR Project to the Krishna Drinking Water Supply Project.
- The Government vide G.O.Ms.No.19, dated: 5-2-2003, I&CAD Department (PW-NSP) has issued orders allocating 3.3 TMC (consumptive use out of 16.5 TMC of water) to the Krishna Drinking Water Supply Project to Hyderabad Metro area by way of allocation from the enblock 811 TMC allocated to the State of Andhra Pradesh under the terms of Krishna Water Dispute Tribunal Award by making re-allocations.
- The Government vide G.O.Ms.No.142, dated: 27-9-2003, I&CAD Department (PW-SLM) has issued orders permitting the Chief Engineer, Projects, Neelam Sanjeeva Reddy Sagar Project, Hyderabad, to construct a control sluice cum regulator at Ch.26.238 Km of AMRP Main Canal to feed raw water to the Water Treatment Plant at Kodandapur.
HYDERABAD METROPOLITAN WATER SUPPLY AND SEWERAGE BOARD
Krishna Drinking Water Supply Project
Administrative Sanction:
The Administrative sanction has been accorded by the Government of Andhra Pradesh vide G.O.Ms.No.559 MA, dated: 23rd Nov'2001 of MA&UD Department, for taking up the Stage-1, Phase-I of Krishna Drinking Water Supply Project at a cost of Rs.875 Crores and expected to cost about Rs.1000 Crores including IDC.
i) |
Cost |
- |
Rs.875.00 Crores* |
ii) |
Cost including interest during construction |
- |
Rs.1000.00 Crores |
Funding Pattern:
i) |
Rs.300.00 crores |
- |
Govt., Grant |
ii) |
Rs.350.00 crores |
- |
HUDCO Loan |
iii) |
Rs.350.00 crores |
- |
Term Loans & Bonds |
* The Project Cost is expected to come down to Rs.820.00 Crores only including IDC due to less tenders received for the various works.
Revised Funding Pattern for Rs.820.00 crores:
i) |
Rs.245.00 crores |
- |
Govt., Grant |
ii) |
Rs.350.00 crores |
- |
HUDCO Loan |
iii) |
Rs.225.00 crores |
- |
Bonds |
5.0 Financial Status: (As on 30-11-2003)
- HUDCO sanctioned Loan of Rs.350.00 Crores in Dec'2002, and out of which HUDCO sanctioned Bridge Loan of Rs.150.00 Crores.
- The Government released Rs.103.36 Crores so far.
- For Rs.50.00 crores of Tax free bonds permission from GOI is expected shortly. Towards balance Rs.175.00 crores several Banks have come forward offering Term Loans at 9% interest. (the total offers are to the extent of Rs.500.00 crores).
HYDERABAD METROPOLITAN WATER SUPPLY AND SEWERAGE BOARD
Krishna Drinking Water Supply Project
Components of the Project:
a) Phase-I - Stage-1:
- Period of implementation 2002 - 2004
[To add additional 45 Mgd of Treated Water]
- Pipeline to transmit treated water - 90 Mgd
- Water Treatment Plant - 45 Mgd
- Pumping equipment - 45 Mgd
- Length of pipeline - 116 Kms
- Lift - 406 Meters
- Power Requirement - 13 MW
b) In the present Project i.e. Phase-I, Stage-1, the pipelines are designed to transmit 90 Mgd of treated water, with capacity of water treatment plant and clear water Pumping equipment limited to 45 Mgd only. The raw water tapping is from Ch.26.328Km of AMRP Main Canal through pipeline to transmit required raw water throughout the year to the Water Treatment Plant at Kodandapur. (In Stage-2, further 45 Mgd capacity of Water Treatment Plant and Clear Water Pumping Equipment would be added, with independent raw water off-take arrangements at Shunkishala in the foreshore of Nagarjunasagar Reservoir with required raw water pumping arrangements and pipeline)
i) Raw Water Transmission:
2200 mm dia MS gravity pipeline inlined and outcoated with cement mortar - 900 Rmt long to transmit raw water through an independent control cum regulating sluice from AMRP Main Canal to the proposed Water Treatment Plant at Kodandapur.
ii) Water Treatment:
45 Mgd capacity with 20% overloading facilities Water Treatment Plant at Kodandapur including a 9 ML capacity Raw Water Reservoir, pre and post chlorination facilities.
iii) Treated Water Transmission:
- 2200 mm dia MS pipelines inlined out coated with cement mortar in Four Packages capable of transmitting 90 Mgd of treated water from WTP at Kodandapur to join the existing water supply system of Hyderabad at Santoshnagar 'X' Roads - 116 Km long. (Transmission System consists of 77Kms Pumping Main, 39 Kms Gravity pipelines)
- Three Stage Clear Water Pumping against a total static lift of 406 mt with each six (6) units of Pumping Equipment (including 50% standby with required surge protection systems with HT Sub-stations) at Kodandapur, Nasarlapally and Godakondla.
- Clear Water Reservoirs 3 Nos of 9 ML capacity each at Kodandapur, Nasalrapally, and Godakondla en-route along with clear water pump houses for housing the Clear Water Pumping Equipment
- Master Balancing Reservoirs 2 Nos of 22.5 ML capacity each at Gunagal
- Terminal Balancing Reservoir of 18 ML capacity at Sahebnagar Kalan
- Extension of power lines to the three pumping stations
Status of the Project (Stage-1 of Phase-I):
The entire Project is programmed to be completed by 31st Mar'2004.
Physical Status (30th January'2004):
i) Pipelines:
- Size - 2200 mm dia
- Length - 116 Kms
- MS pipes fabricated - 110 Kms long (94%)
- MS pipes laid - 98 Kms (85%)
ii) Water Treatment Plant (45 Mgd capacity):
Work under progress. Programmed to be completed by 31st Mar'2004.
Civil Works - 75% completed Mechanical Items - 40% supplied
iii) Six Enroute Reservoirs at 5 places (90 ML capacity):
Works under progress and 70% completed. Will be completed by end of February 2004.
iv) Pump Houses at 3 places:
Works under progress and 70% completed. Will be completed by Feb'2004.
v) Pumping Equipment at 3 places:
Work let out and programmed to be completed by end of Mar'2004. Manufacturing pumps, motors, panel boards etc., under progress.
vi) Electrical Sub-stations at 3 places:
Work let out and programmed to be completed by end of March 2004. The manufacturing of Transformers is under progress and Civil Works under progress.
Financial Status:
Expenditure to the end 30th January'2004 - Rs.345.00 Crores
Krishna Drinking Water Supply Project
Sage-1, Phase-I Bringing 90 Mgd (410 Mld) of treated water to twin cities of Hyderabad & Secunderabad by tapping AMRP Main Canal at Km.26.328 including Stage-2 works proposed to be advanced in Stage-1
ABSTRACT COST ESTIMATE (Stage-1, Phase-I)
Particulars |
Rs in Crores |
(I) Capital Cost |
|
1. |
Off take and Raw Water Gravity Main |
4.00 |
2. |
Water Treatment Plant (90 Mgd) |
48.00 |
3. |
Pipeline for 116 Km (90 Mgd) |
418.00 |
4. |
Enroute Reservoirs (117 ML) at 5 locations |
39.00 |
5. |
Pumping Stations |
9.00 |
6. |
Pumping Equipments |
61.00 |
7. |
Extension of Power Lines and Substations |
54.00 |
8. |
Miscellaneous Items |
23.00 |
9. |
Purchase of Shares in Power Generation |
50.00 |
|
Sub-Total (I) |
706.00 |
(II) |
Quality Control Changes & Change in design features |
1.00% |
2.00 |
(III) |
Physical Contingencies |
1.00% |
10.00 |
(IV) |
Price Contingencies |
1.00% |
10.00 |
|
Sub-Total (II) |
- |
22.00 |
(V) |
Administrative & Preoperative Expenses |
|
32.00 |
TOTAL: |
760.00 Crores |
Advancing certain components of the Stage-2 of Phase-I into the Stage-1 of Phase-I Project:
The total actual cost of the Stage-1, Phase-I Project has come down due to less tenders received and also due to saving in the cost of extension of the power supply lines etc. Hence it is proposed to advance the components pertaining to (i) Additional Storage Reservoirs at 3 places along with the (ii) Additional Pumping Equipment at the three pump houses and another (iii) 45 Mgd of water treatment plant at Kodandapur all together costing about Rs.62 Crores, and take up and complete the same in Stage-1, Phase-I of the Project itself so that 90 Mgd of additional water could be made available in the water supply system and to make the project more viable. The total cost of the Stage-1 including these components proposed to be advance from Stage-2 is estimated to cost only Rs.820 Crores as follows.
Particulars |
Rs.in Crores |
Capital Cost |
760.00 |
Lenders Fees |
6.55 |
Interest During Construction |
53.00 |
Total |
819.55 or say Rs.820.00 Crores |
HYDERABAD METROPOLITAN WATER SUPPLY AND SEWERAGE BOARD
Krishna Drinking Water Supply Project
Components of Stage-2, Phase-I Project:
Sl. No. |
Component |
Cost (Rs. Crores) |
i) |
Independent Intake Tower and Raw Water Pumping Station for all the three Phases i.e. 16.5 TMC, including Raw water Pumping Equipment for Phase-I i.e. for 5.5 TMC in the foreshore of Nagarjunasagar Reservoir. |
80.00 |
ii) |
2200 mm dia MS Raw Water Pumping Main from the Raw Water Pumping Station at Sunkishala to WTP at Kodandapur to a length of about 17.5 Kms. |
70.00 |
iii)a |
Additional 45 Mgd capacity Water Treatment Plant (WTP) at Kodandapur |
25.00 |
b) |
Construction of additional 3 Nos of Clear Water Reservoirs each of 9 ML Capacity at Kodandapur, Nasarlapally & Godakondla. |
12.00 |
c) |
Procurement and erection of additional Clear Water Pumping Equipment at each of the three Clear Water Pumping Stations at Kodandapur, Nasarlapally & Godakondla for pumping additional 45 Mgd of treated water |
25.00 |
|
Total: |
212.00 Crores |
|